Capital Project Management Program

The scope of infrastructure improvements required over the first 10 years of the planning period exceeded $800 million.

Capital Project Management Program

Completed in 2013, this large metro wastewater system required operational support to meet more restrictive discharge permit standards while the existing treatment facility was undergoing major renovation.

capital-project

Overview

The services provided by Black & Veatch include program management and planning of a large metro wastewater system.



Planning considerations and requirements:



  • The scope of infrastructure improvements required over the first 10 years of the planning period exceeded $800 million.

  • Upgrades to treatment and collection system were made under multiple contracts and included roughly 70 projects.

  • Planning included operational support to meet more restrictive discharge permit standards while the existing treatment facility was undergoing major renovation.

  • The project effectively managed the capital expenditure schedule to allow cash funding where practical and maintained a reasonable rate structure.